AUGUST WORKS NOTICE
SHARE

Please note that these are subject to change due to weather and/or operational impacts. 
Works are continuing to progress for The Children's Hospital at Westmead (CHW) Stage 2 Redevelopment, with works for the new Paediatric Services Building now well underway,  while work continues on refurbishing some existing areas of the hospital. This work includes:
  • Superstructure works have been completed, whilst services and fit-out works are continuing on the Paediatric Services Building (PSB). Façade installation is ongoing with the tower underway and internal demolition has commenced in the former Cancer Research Centre and Gait Lab spaces . The first of the PSB tower cranes is to be dismantled around mid-late August.
  • Works are underway within the existing hospital for refurbishments (Kids Pathology and Central Specimen Reception Area/Blood Bank). In addition, works for the level 3 linkway corridor widening have progressed with external works for façade and structure underway..
The ‘KidsPark’ forecourt is scheduled to open in the coming months.
In addition, works for the Viral Vector Manufacturing Facility (VVMF) Stage 2 including services and wall installation within and façade installation ongoing around the Kids Research (KR) building. Construction works including stormwater diversion works are continuing within the Innovation Centre.
 
Pedestrian and traffic changes
You may notice increased construction vehicles within Kid’s Research Lane due to works being carried out in the area.
 
Staff who travel through this area to access Hawkesbury Road and staff car parks will need to use an alternative route.  
 
Access will remain open between CHW and KR via Level 2, and to the KR loading dock and plant rooms.
 
The CHW bike cage will remain open and accessible. For the safety of bicycle users, entry is via the rear of the hospital and walk through the Genetics Corridor, or alternatively enter from the main entrance. Access to the CHW bike cage and Chinese Gardens via Research Road will be closed until several key construction projects are complete. 
 
As always, please follow direction of signage and site staff for your safety. There may be some changes to traffic conditions while work is taking place including intermittent stoppages and lane closures. 

Motorists are reminded to slow down to 20km/h while travelling along Redbank Road. 
 
Our work hours
This work will occur during standard construction hours (Monday to Friday from 7am to 6pm, Saturdays 8am to 5pm). We will provide further notification of any work that is required to take place outside of these hours.

How we will manage works
For your safety, please stay on marked paths, and follow the signs or any directions from site staff during construction. 

Noise, dust and vibration will be closely monitored. This includes mitigation measures such as:
  • A Class and B Class hoardings
  • Programming noisy works to occur during the day
  • Noise and vibration monitors
  • Water trucks to manage dust
  • Noise blankets

For more information on what’s happening around the construction site, you can visit our map

We thank you for your patience while this project is underway.

Documents
The Children's Hospital at Westmead August resident notification.